3.In Probability and Impact Metrics which of the following statement is true?

A. For opportunities, the high risk (dark grey) zone offers greatest benefits

B. For opportunities, the low risk (medium grey) zone offers lowest risk and best benefits

C. for Risks the high risk (dark grey) zone offers greatest benefits

D. for Risks the low risk (medium grey) zone should be addressed first

关于概率和影响矩阵,下列哪个说法是正确的?

A.对机会而言,高风险(黑灰色)区域意味着代表最大的利益

B.对机会而言,低风险(中灰色)区域意味着最低的风险和最好的利益

C.对风险而言,高风险(黑灰色)区域意味着最大的利益

D.对风险而言,低风险(中灰色)区域应该必须首先确定

4.Zero defects practice or Do it first time is associated with which of the following?

A. Crosby

B. Juran

C. Deming

D. Shewhart

零缺陷或者事情一次作对和下列哪个有关?

A.克劳斯比

B.朱兰

C.戴明

D.休哈特

5.Which of the following would be the BEST description of project management plan?

A. It contains risk, cost, process improvement and other management plans.

B. It is one of the outputs of project management software.

C. it is milestone.

D. it is project scope statement.

下列哪个最好的描述了项目管理计划?

A.包括风险、成本、过程改进和其他管理计划

B.是项目管理软件的输出之一

C.是里程碑

D.是项目范围说明书